Tuesday, December 12, 2006

Progress Update 12/12/06

A quick update on the building work. Things seem to be progressing quite well again but Christmas is fast approaching so we are likely to see a lull in the work for several weeks. The existing ground floors have been removed after much debate (& expense!) and under floor ventilation/insulation has been installed. The waste pipes for all the plumbing are going in (although not exactly in the positions agreed!) and conduit for the electrical cables is also being installed. Reinforcing rods are also going down on the first floor ready for the concrete to be poured. I have a meeting on site with the builder on Friday to clarify a few issues as they currently appear to be working from two different sets of plans and are therefore making errors with the layout of services.